Read-only demo

A client's project page

This is what the family behind HB-024 sees when they open their Studio. Figures are illustrative.

HB-024 · My project

Rayfield Residence

First floor
Current stage
Roof · Nov
Next milestone
₦18.4m
Next payment
  1. FoundationDone 14 Mar
  2. Ground floorDone 30 May
  3. First floor80% · Oct · 80% complete
  4. RoofNov
  5. FinishesJan
  6. HandoverMar

Site log

  • Fri 19 Sep

    First-floor slab formwork complete; rebar inspection passed.

  • Fri 12 Sep

    First-floor blockwork up to lintel level on the east side.